DNAPL REMEDIATION

SILRESIM Superfund Site

Current Environmental Solutions is a wholly owned subsidiary of Terra Vac Corporation offering the Six-Phase Heating™ / Electrical Resistance Heating technology.

Abstract

TerraVacs subsidiary, Current Environmental Solutions (CES™) was subcontracted by Foster Wheeler Corporation (FW) to implement the Electrical Resistance Heating (ERH) technology using Six Phases (SPH™) as a pilot study system at the Silresim Superfund site in Lowell, MA.  CES was formed by TerraVac Corporation in 1997 as a technology pipeline for the new Six Phase Heating™ technology.   The subcontract was executed in July 2002, and actual site work took place between August 2002 and January 2003.

The subsurface soil and groundwater have been impacted by a variety of volatile and semi-volatile compounds.  VOCs are comprised of both dense and light non aqueous phase liquids (DNAPL and LNAPL).  The DNAPL compounds consist of a wide variety of volatile and semivolatle contaminants including chlorinated solvents and PAHs.  The LNAPL compounds consist of aromatic compounds including BTEX and styrene.  The contamination is a result of heavy industrial use since the 1900’s, but the most significant cause of the contamination was due to operations of the Silresim Company solvent waste recovery facility that operated from 1971 through 1977.  The Silresim Company declared bankruptcy in 1977 and abandoned one million gallons of hazardous materials on site. 

The pilot test area was located in an area known to have high levels of VOC contamination in soil and groundwater.  The area of the one array pilot study was approximately 850 ft².  The depth of treatment extended to 40 ft below grade surface (ft bgs).  The subsurface consists of silty sand from grade to ten ft bgs followed by a varved silty clay unit that extends to 40 ft bgs.  Groundwater is typically found at 6 ft bgs.  The main objectives of the study were to prove the efficacy of the ERH technology as a remedial alternative at the site by significantly reducing soil and groundwater concentrations. 

The ERH system was designed to heat and decontaminate soil and groundwater within the 850 ft2 area from grade to 40 ft bgs, corresponding to a total treatment volume of soil and groundwater of approximately 1,250 yd³.  The subsurface installation consisted of 7 deep and 7 shallow vented electrodes, 4 horizontal vacuum extraction (HVE) wells, 4 thermowells, and three clusters of groundwater monitoring wells.  Above surface equipment included a 500 kW Six-Phase Heating™ Power Supply Unit (PSU), an electrolyte addition system, a steam condenser system, granular activated carbon (GAC), and a water collection and transfer system for managing secondary wastewater on site.

Installation of the ERH system commenced in August 2002.  System start-up began in early October 2002.  Heating operations were completed over a three-month period ending early January 2003.  Boiling temperatures were achieved after 5 weeks of operations.  Based on field screening techniques, approximately 1,500 pounds of vapor phase volatile organic compounds (VOCs) were removed during the test.  Based on soil analytical results and mass removal estimates performed by FW, the mass in the target treatment area was estimated to be 660 lbs and the post treatment mass in the target area was estimated to be 13 lbs.  Additional contamination was degraded as indicated by high levels of chloride ion in the groundwater.  As a result, shallow groundwater contamination located in the target treatment zone was reduced by greater than 99% (to 24 feet bgs) and greater than 77% in deeper groundwater contamination.  Total electrical energy input was approximately 286,200 kWh or 93% of the predicted value. 

The ERH pilot test functioned extremely well.  The core component for the application of the technology, the electrodes, was very efficient at coupling power to the soil.  There were never any signs of power degradation.  The spacing of the electrodes as well as the diameter of the electrode bore was adequate as well.  These sizes were based on conventional design parameters CES™ routinely uses.  Site heat-up also progressed well.  During uninterrupted heating phases, temperature heat-up rates were typically above 5ºC per day.  Based on the performance of the electrodes, the spacing of the electrodes could be increased to 17.5 ft spacing.

Contaminant Levels at Beginning and End of treatment.

The subsurface soil and groundwater at the site is impacted with volatile organic compounds (VOCs) such as Trichloroethene (TCE), 1,1,1- Trichloroethane (TCA), and other chlorinated aliphatic and aromatic compounds.   Dense non-aqueous phase liquid (DNAPL) was detected in the pilot area and in other areas surrounding the pilot site.  The SPH pilot system was used to remove VOCs through direct vaporization, in situ steam stripping and thermally enhanced degradation. 

The reported initial mass in place was 800 lbs, however, the SPH system removed 1600 lbs during operations.  Based on chloride increases, as much as 1600 lbs may have been degraded in place.  As a result of the ERH treatment, the shallow groundwater concentrations at MW717, 4 to 24 ft bgs, showed a 100% removal of TCE, 100% removal of TCA, with an overall total VOC removal rate of 99.7%.   One month after the end of operations, the groundwater concentrations drifted up slightly resulting in a total VOC reduction of 93%. 

In the lower portions of the treatment zone (i.e. 27 to 37 ft bgs and 40 to 50 ft bgs), there were significant reductions in CVOCs at 92% and 79% respectively.  Sharp increases in acetone reduced the total VOC percentage removal to 84% and 39%, respectively.  These results may have been impacted by the potential influx of contamination from outside of the pilot which may have contributed to the rebound in groundwater. 

Groundwater Treatment Standards and Levels Achieved

The main goal of the SPH pilot study is to lower the VOCs levels by greater than 99% from pretest levels during a set treatment duration.  Another important goal is that of maintaining effective vapor control of the SPH process.  The system removed more than double the reported mass in place, while nearing or surpassing the 99% concentration reduction in all monitoring points.

Geology and Soil Types Encountered

The site soils consisted of fill and fine sand from grade to 10 ft below grade (bg), clay clay and silt layers from 10 to 30 ft bg, then silt and sand layers from 40 to 50 ft bg.  Groundwater was encountered between five and ten ft. 

Treatment Times Required to Meet Defined Treatment Standards

The set duration for this pilot test was 90 days of operations.  During this time, the system removed more than double of the reported mass in place.



This page and contents © Copyright 2001 by Terra Vac Corporation. ALL RIGHTS RESERVED