Petroleum Refinery - Casper, WY

Scope of Services Provided:

  • Remedial Investigation
  • Free Product Recovery
  • Vacuum Extraction
  • OxyVACSM
  • Groundwater Monitoring
  • On-site Gas Chromatograph
  • OSHA-trained Personnel

Role: Prime to Owner

Date Completed: November 1990

Hydrocarbon contamination was detected in a tract adjacent to this petroleum refinery in September 1988. As a result of the contamination, Terra Vac was contracted by the owner to perform a remedial investigation, and to remediate the hydrocarbon-impacted soils. Gasoline, diesel and jet fuel had been identified in the contaminant plume.

Terra Vac began the remedial investigation in May 1989 by installing a total of 72 wells (a combination of groundwater monitoring and vacuum extraction wells) within and around the refinery to determine the source of the hydrocarbons and to delineate the extent of the subsurface hydrocarbon plume. Additionally, Terra Vac performed aquifer testing to determine its hydraulic characteristics.

The subsurface was characterized as a relatively homogeneous, thin, upper layer of clayey silt and fine sandy silt, from 4 to 8 feet below the ground surface. Beneath the upper soil layer was a lower layer of medium-to-coarse grained sands which varied from 30 to 60 feet in thickness. The depth to groundwater varied from 25 to 30 feet in the investigation area.

Samples taken during the remedial investigation showed that the groundwater and soils were impacted by hydrocarbons characterized as a mixture of gasoline, diesel and jet fuel as well as some heavy oils. The hydrocarbon plume in the groundwater was estimated to be one mile in length. The lateral and vertical extent of the hydrocarbons in the soil was extensive. The extent of the contamination was attributed to multiple sources and the transmissivity of the groundwater aquifer. The remedial investigation showed that the hydrocarbon concentrations were a result of transport along the surface of the water table. The data was used to identify several likely sources on the site.

Terra Vac installed a pilot vacuum extraction system to remove free product, provide source control, and capture vapors prior to their release to the atmosphere. Terra Vac also mobilized a catalytic oxidation unit to treat all extracted vapors.

Over an operating period of 20 days, this pilot system removed over 10,000 pounds of hydrocarbons (equivalent to 1,430 gallons of gasoline) at a flowrate of 1,000 standard cubic feet per minute. The measured radius of influence from the extraction wells was approximately 80 feet.

Based on this initial pilot test, the system was expanded in December 1988 and again in May 1989. Remediation activities at this site continued until November 1990 and recovered a total of 204,000 pounds of hydrocarbons over a 25-month operating period. In addition, the presence of liquid-phase hydrocarbons were substantially reduced.


Upjohn Superfund Site - Barceloneta, PR

Scope of Services Provided:

  • Remedial Investigation RI/FS Report
  • Feasibility Testing Design
  • Vacuum Extraction
  • Spray Aeration Water Treatment
  • On-site Gas Chromatograph

Role: Prime to Owner

Date Completed: March 1988

The Upjohn Superfund site in Barceloneta, Puerto Rico was the first, and as of April 1992, the only Superfund site to have soils completely cleaned (over a 30 month period) by the vacuum extraction (VE) technology. The contaminant removed from this site was predominantly carbon tetrachloride (CCl4) which leaked from an underground storage tank located in an industrial tank farm. Contamination was found as deep as 300 feet in the unsaturated zone and had already reached the aquifer when the subsurface investigation had begun.

The subsurface at the site consisted of a karst limestone, containing a primary drinking water aquifer. The typical subsurface profile of the area contained surface deposits from 40 to more than 200 feet, consisting of residual silt and clay. Soil hydraulic conductivities ranged from 10E-5 to 10E-7 cm/sec. Beneath this formation were limestone formations which contained the unconfined aquifer. The water table was at a depth of 300 feet.

As groundwater recovery operations were initiated to control migration within the aquifer, a pilot vacuum extraction system (VES) consisting of three wells was designed and installed to determine the radius of influence of the extraction well and to test the efficacy of the innovative system. After seeing extraction rates of raise to 250 pounds per day, additional wells were installed to complete the full-scale system that was used at the site.

Terra Vac's founder, Mr. James Malot, was instrumental in the design and implementation of the VES at this site. The full-scale system included 31 VE wells and six vacuum extraction units. The VES was capable of up to 29.9 inches of mercury and a total of 1,000 cubic feet per mintute. Nearly 18,000 gallons of CCl4 were recovered during the remediation. An additional 8,000 gallons were extracted during a pilot study operated from January 1983 to April 1984. The total volume of soil treated at this site was over 1,000,000 cubic yards, and the VE process was credited with remediating 90% of the original spill volume.

The site was closed in March 1988 when three months of operations occurred with non-detect levels of CCl4 in the extracted air stream. EPA confirmed lab results showed less than 0.01 parts per million in the soils. Initial soil concentrations had been in excess of 2,000 ppm.

The success seen at this site and other concurrent applications resulted in Mr. Malot and Upjohn applying for and receiving two patents for the process of VE to remove volatile organic compounds from the subsurface.


Dry Cleaner - Springfield, MA

Scope of Services Provided:

  • Environmental Assessment
  • Remedial Investigation
  • Dual Vacuum Extraction
  • Vacuum Extraction
  • Tank Removal
  • Source Control
  • Vapor Phase Carbon
  • OSHA-trained Personnel
  • Groundwater Treatment
  • On-site Gas Chromatograph

Role: Prime to Owner

Date Completed: February 1994

Contamination at this operating dry cleaning plant resulted from the release of chlorinated solvents, primarily tetrachloroethylene (PCE, PERK), to the soils under the plant. The groundwater also was impacted by the overlying soil contamination. Site characteristics included 20 feet (6 meters) of sandy soils overlying bedrock, and groundwater was approximately eight feet (2.4 meters) below ground surface.

The cleanup was conducted under an Interim Measure (IM) to establish source control through the remediation of the site soils. The cleanup goals for the soils were 500 µg/kg [parts per billion (ppb)] with groundwater to be cleaned to 3 mg/l [parts per million (ppm)]. PCE cleanup was completed in-situ, without excavation.

To minimize the remediation time and overall project costs, Terra Vac implemented a phased remedial approach for the site. Terra Vac's scope of work completed the assessment/investigation while implementing dual vacuum extraction (DVE), a proven technology for remediating PCE-contaminated sites. This integrated approach enabled Terra Vac to provide the most rapid and cost effective remediation of the client's site. Terra Vac began operations in March 1993 with the removal of a 5,000-gallon (20,000-liter) heating oil tank. The system for the IM used five DVE wells to address the contamination under the building. All DVE wells were placed below grade around the perimeter of the building to minimize impacts on parking and pedestrian traffic.

Operation of the DVE remediation system commenced in August 1993. In the first three months of operations, 200 pounds (90 kg) of PCE were removed. All extracted vapors were treated through the dry cleaner's on-site activated carbon/steam regeneration facility until a decline in the vapor-phase concentrations led to the demobilization of the vacuum extraction equipment in December of 1993. Approximately 240 pounds (110 kg) of PCE were removed from the site. All extracted groundwater was treated with liquid phase activated carbon prior to discharge to a storm drain. Terra Vac continued groundwater treatment until February 1994.


International Airport - Jamaica, NY

Scope of Services Provided:

Role: Prime to Owner

Date Completed: Ongoing

Subsurface contamination of this former airline terminal resulted from the release of jet fuel to the subsurface due to spills and leaks associated with the hydrant fueling system, and to a lesser degree from underground storage tanks containing motor fuel, heating oil and ethylene glycol. The site is covered by 1 to 1.5 feet (30 - 45 cm) of reinforced concrete, with the subsurface comprised of fine to medium sands and trace quantities of silt. This stratigraphy is present at depths ranging from 11 to 14 feet (3.3 - 4.2 m) below grade and is underlain by a thin, low permeability, clayey-peat layer. The depth to groundwater ranges from 6 to 8 feet (1.8 - 2.4 m) below grade. Free product is also present floating on the groundwater table.

Terra Vac is under contract to design, construct, operate and maintain a high vacuum, dual phase extraction system (HVDPE) to address contaminated soils and recover free product found at several locations at the site. The project consists of two phases. Phase I required the rapid mobilization and construction of the system to meet the owners' construction schedule. The construction of the Phase I system is complete. Startup was in July 1994. As a result of the HVDPE system effectively dewatering the saturated zone, Terra Vac has instituted a bioventing system [BIOVACSM] system to address semi-volatile compounds in the subsurface.

The Phase I recovery system consists of two separate systems, including a total of 51 HVDPE wells outfitted with jet pumps, 29 air injection wells for groundwater sparging and/or bioventing, two 50 horsepower (37.5 KW) high vacuum extraction units capable of 1,000 standard cubic feet per minute (scfm) [1.650 normal cubic meters per hour] airflow, and a vacuum extraction unit for air injection. The off-gas treatment systems consist of a catalytic oxidation unit capable of 1,000 scfm air flow and four 1,000-pound (300 kg) vapor phase, granulated activated carbon canisters.

The major components of the groundwater treatment system include liquid/vapor separators, product recovery tanks, iron oxidation tanks, inclined plane clarifiers, sludge holding tanks, centralized groundwater recovery equalization tanks, a 100 gpm (23 m3/h) air stripper and six 1,000-pound (300 m) liquid phase granulated activated carbon canisters.

A data acquisition system is also on-line to monitor the vacuum, air flow, pressure (pumps) and levels of sludge and/or free product. The data acquisition system also notifies Terra Vac in the event of a system or component shutdown or malfunction.

The Phase II system, which is currently under design, will be comparable in size to the Phase I system. The Phase II system will be constructed after contractors complete the demolition of the terminal building. The construction of the Phase II system is currently scheduled to commence in the Spring of 1995.


Former Service Station - Denver, CO

Scope of Services Provided:

Role: Prime Contractor to Seller

Contamination Type: Gasoline

Date Completed: July, 1994

Terra VacÕs remediation system was designed for removal of gasoline from soil and ground water beneath a vacant gas station during construction of a new commercial building at the site. All subsurface piping and well head locations wer precisely surveyed and placed >4 feet deep to prevent interference with future building foundations, footings, etc. Once building construction began, direct access to well heads was prohibited, consequently, remote well heads and manifold systems were designed for individual well head control and monitoring from a point outside of the building footprint.

Terra VacÕs proprietary automatic entrainment devices, designed for maintenance-free extraction of gasoline contaminated vapors and ground water, were installed in 21 Dual Vacuum Extraction (DVE) wells located beneath the building footprint. A second well casing was additionally installed in three DVE wells for extraction of shallow soil vapor contaminants. Remediation system components included a 40 horsepower vacuum extraction unit capable of 500 SCFM air flow; a 200 gallon vapor/liquid separator equipped with an internal air sparging device; and a 200 pound liquid phase carbon bed capable of up to 10 gallons per minute of water flow. As water quality levels prior to the carbon polish system never exceeded discharge requirements, the carbon polish system was taken off-line after three months of operations. Contaminant recovery was conducted at an average well head vacuum of 5 inches of mercury and an averge airflow of 20-40 standard cubic feet per minute per DVE well. Above ground components of the water treatment system were equipped with tank heater, heat tape, and pipe insulation to prevent freezing during winter operations.

During five months of remediation system operation, approximately 5,000 lbs of gasoline were extracted. One well containing free product was reduced to a ground water concentration of 36 ug/L of benzene in just 21 days. In spite of intermittent down time due to system damage by the building construction contractor, the auto entrainment devices operated flawlessly. Regulatory site closure is pending based on a year of ground water monitoring.


Property Development - Syracuse, NY

Scope of Services Provided:

  • Ground Water Pump Tests
  • Activated Carbon System
  • Design of Ex situ Treatment Cells/Liners
  • Soil Gas Surveys
  • OxyVACSM
  • Vacuum Extraction
  • Dual Vacuum Extraction
  • Ground Water Monitoring System
  • Underground Well Installation
  • Integrated Ground Water Extraction and Treatment Systems
  • On-site Process Control
  • OSHA Trained Personnel

Role: Prime Contractor to Owner

Date Started: February 1990

Between September 1988 and February 1990, Terra Vac was contracted to test the efficacy of the dual vacuum extraction process in cleaning waste yard soils containing high levels of chlorinated VOCs. The area was being considered for commercial development and required immediate attention under a tight schedule.

The soils at the site were highly heterogeneous, consisting predominantly of clays and chemical wastes resembling chalk deposits (e.g., calcium carbonates, oxides and sulfates), Permeabilities ranged from 10E-4 to 10E-8 cm/sec. Contaminants included TCE, tetrachloroethane, methylene chloride and vinyl chloride.

A short, one-week pilot program was conducted and consisted of five DVE wells and the associated activated carbon water treatment systems. This pilot was immediately expanded to evaluate ex situ vacuum extraction of stockpiled soils in cells designed by Terra Vac, and variations of ground water extraction integrated with DVE. The integrated system consisted of horizontal subsurface recovery networks as well as a wellpoint recovery network. Operation of the ground water treatment system was also significantly upgraded to treat up to 60 gpm of influent.

While several systems of varying size were installed and operated during the course of the three-month operating period, ultimately, three main vacuum extraction systems were designed, constructed and operated by Terra Vac: one for the treatment of excavated and stockpiled soils for ex situ treatment, one for the DVE wells and dewatering wellpoints, and one for a horizontal DVE trench recovery network. This network consisted of 15 trenches ranging from 200 to 4,000 feet in length.

The full-scale vacuum extraction system consisted of 12 vacuum extraction units operating at a design flow rate of 3,000 SCFM at 14" Hg and achieved extraction rates of up to 400 pounds per day. Extracted vapors were primarily treated with a multiple stage activated carbon system, but was complemented late in the project by a catalytic oxidation unit.

In a three-month operating period, approximately 9,000 pounds of chlorinated VOCs were extracted and treated, representing an 80 percent reduction in the soil concentrations. An additional 1.5 million gallons of ground water were treated, resulting in removal of approximately 750 pounds of VOCs from the aqueous phase. After this operating period, the soils were determined to be treated to acceptable risk levels. This resulted in the NYSDEC approving the excavation of the soils to allow for the construction of the foundation for a shopping center.


Microelectronics Manufacturer - San Jose, CA

Scope of Services Provided:

Role: Prime Contractor to Client

Date Started: April 1992

Terra Vac is providing the client with remedial services to clean-up their San Jose site impacted with SHELLSOL, NAPHTHA and Freon. The site consists of a complex lithological setting soil and groundwater impacted with semi-volatile organic compounds and solvents.

The remedial system incorporates pneumatic soil fracturing, hot air injection, Dual Vacuum Extraction and vapor extraction technologies.

The remedial system includes, 3-40 Hp vacuum extraction blowers, 30 VE wells, 40 Dual Vacuum Extraction wells and 20 Hot Air Injection wells. The injected air stream will be heated to 650 degrees Fahrenheit by electric heater banks. These innovative technologies have increased contaminant mass extraction rates by more than 10-fold.


Aerospace Company - Fullerton, CA

Scope of Services Provided:

Role: Subcontractor to A/E firm

Date Started: January 1993

Terra Vac's Western Region is currently involved in the cleanup of a large chlorinated plume under an aerospace facility in California. The site has a complex lithology (heterogeneous soils, perched water, etc.) with contamination as deep as 120 feet. Additional constraints include the location of the chemical plume under two buildings that required the installation of all wells below grade.

A pilot soil vacuum extraction project was completed in September 1991 and consisted of 11 wells within four borings at the site. Terra Vac has recovered over 20,000 pounds of vapor phase chlorinated organic compounds over the one-year operating period.

Based on the success seen during the pilot a total of 120 wells have been constructed within 50 borings at the site. The complexity of the lithology will required up to three wells per boring. All extracted vapors will be treated with an activated carbon system prior to discharge. To date 3,000 pounds of vapor-phase chlorinated organic compounds have been removed.


Dry Cleaning Facility - Santa Barbara, CA

Scope of Services Provided:

  • Vacuum Extraction
  • Vapor Phase Carbon
  • On-site Gas Chromatograph
  • On-site Laboratory
  • OSHA-trained Personnel

Role: Prime to Owner

Date Completed: August 1991

During demolition activities in 1988, chlorinated hydrocarbon contamination was discovered in the soils at this former dry cleaning facility. A subsequent site investigation confirmed the presence of chlorinated hydrocarbons in both the subsurface soils and the groundwater. Further investigation to delineate the plume also identified the presence of petroleum hydrocarbons.

Based upon the site assessment reports, Terra Vac designed a two-phase vacuum extraction system (VES). Phase I, a pilot to demonstrate the feasibility of the technology, consisted of three vacuum extraction (VE) wells, a vacuum extraction unit, a vapor/liquid separator and two 1,000-pound vapor carbon treatment units. This design took advantage of the depressed water table caused by California Department of Transportation's dewatering system. Phase II, implemented upon approval of Phase I results, expanded the system to full-scale with the addition of four wells.

The system operated from April 1991 through August 1991, removing approximately 1,200 pounds of both petroleum and chlorinated hydrocarbons. The extracted vapor concentrations were reduced 90 to 99% from initial levels.

Laboratory analyses of soil samples taken from confirmatory borings showed the effective remediation of the soils. Tetrachloroethylene (PCE) was reduced to levels of 0.26 parts per million (ppm) or less in the soil. All final borings showed either no detectable levels of aromatic hydrocarbons or amounts far below Santa Barbara County LUFT Program cleanup levels. Only one sample showed a total petroleum hydrocarbons value slightly higher than the 100 ppm target (120 ppm).


Petroleum Distribution Pipeline - Greensboro, NC

Scope of Services Provided:

Role: Prime to Owner

Date Completed: Ongoing

Terra Vac is operating under contract from a major petroleum distribution company to design, install and operate a vacuum extraction system to remediate soils and groundwater impacted by petroleum hydrocarbons, principally diesel and gasoline. The contamination occurs over a 58,000 square foot area at this site. Groundwater with free product is found at 15 feet below ground surface. The soils at the site have permeabilities as low as 1 x 10-6 cm/sec and consist of saprolites.

Prior to initiating the construction at the site, Terra Vac performed groundwater modeling to determine the design parameters for the full-scale system. A Corrective Action Plan was also devised and submitted to the State Regulatory Agency for approval.

The remedial system consists of 19 dual vacuum extraction (DVE) wells, a 40 horsepower vacuum extraction unit capable of 15 inches of mercury at 750 standard cubic feet/minute (scfm) airflow, a catalytic oxidation unit capable of handling 1,000 scfm airflow, and a groundwater treatment system consisting of an oil/water separator with a shallow tray air stripper capable of treating 20 gallons per minute followed by polishing with liquid phase activated carbon.

Terra Vac completed installation and start-up of the full-scale system in October 1994. Initial vapor-phase VOC extraction rates were as great as 900 pounds per day. Over 80 gallons of liquid-phase petroleum product were recovered during the first week of operations. By the end of December 1994, Terra Vac had removed over 32,000 pounds (approximately 5,000 gallons) of VOCs with the DVE system. Operations are continuing in 1995.



Marshall Army Air Field - Fort Riley, KS Superfund Site

Scope of Services Provided:

Role: Subcontractor to Client

Date Completed: Ongoing

Terra Vac is operatin a full scale vapor extraction and bioventing system at a former firefighting training area (Burn Pit) at Marshall Army Airfield. The site was once used to train military personnel in fighting a variety of fires. This included fixed wing and rotary wing aircraft. The types of fuels used at this location were JP-4, AVGAS, and MOGAS. The mixture of fuels used for fire training have resulted in contamination of soils by several volatile organic compounds (VOCs). The list includes benzene, toluene, ethyl-benzene, xylenes, and solvents such as PCE, TCE, TCA, DCA and methyl ethyl ketone (MEK). The site soil is a silty clay.

The remediation system includes a network of soil vacuum extraction wells, separate piping manifold systems, air/water separators, a 10 hp vacuum extraction blower and vapor phase granulated carbon adsorption vessels.

The bioventing system consists of sparge and vapor extraction wells. An air compressor injects air into the subsurface. The sparge well is surrounded by a series of vacuum wells which removes vapors to the carbon treatment vessels.

Carbon inlet concentrations for this system in the first 26 days of operation were between 1,300 and 1,800 ug/l. The system initially generated approximately 14 pounds of VOCs per day. The bioventing system is averaging 900 to 1,100 pounds of VOCs per day.



Petroleum Distribution Pipeline - Atlanta, GA

Scope of Services Provided:

Role: Prime to Owner

Date Completed: Ongoing

Terra Vac was selected in early 1992 as the Emergency Response Contractor to manage the remediation of soils and groundwater contaminated with gasoline from a ruptured pipeline. The contamination occurred over a 2 acre area, and required the rapid mobilization of equipment and resources to provide source control at the impacted area. Remedial investigation and groundwater monitoring is being performed in conjunction with the remedial action. Terra Vac also prepared and submitted the necessary documents for the approval of the remedial action plan currently underway at the site.

The remedial system at the site currently consists of 23 vertical dual vacuum extraction (DVE) wells, eight horizontal soil vacuum extraction (SVE) trenches and two groundwater extraction wells. Extracted groundwater is being transferred to an oil/water separator for free product recovery prior to its transfer to an air stripper. Extracted vapors are treated by a catalytic oxidation unit capable of treating 1,000 standard cubic feet per minute.

During the 24-month operating period, Terra Vac has extracted and treated over 11 million gallons of groundwater, from which 1,000 gallons of free product have been recovered. Additionally, over 17,000 pounds of vapor-phase product have been recovered.

This phased remedial approach, i.e., construction concurrent with investigation, is critical to the rapid and cost effective cleanup of sites under an emergency situation.


This page and contents © Copyright 2001 by Terra Vac Corporation. ALL RIGHTS RESERVED